Railway North (Northcote to Tuckers) Proposed Cycleway Extension

As at 31/07/2010

Type of project: Street Works 
Status of project: Current 
Project Description: This proposed cycleway and will be an extension of the existing facility south of Northcote Road, and in future it will extend to the Main North Road to the north. The project involves the ....
See a full description below
Current stage: Under Maintenance Contract 
Scheduled to start: 27/02/2010 
and finish: 24/02/2011 

Have Your Say
Consultation name Opens Closes Contact
Railway North (Northcote to Tuckers) Proposed Cycleway Extension
17/11/2008 5:00p.m. 13/12/2008 Brian Boddy, 941-8013

Affects
Areas affected: Uxbridge Street, Cavendish Road, Heaphy Place, Northcote Road, Tuckers Road 
Wards affected: Papanui, Shirley 
People affected: General community 

Links
Map:  
Website:  
Other links:
Railway North (Northcote to Tuckers) Proposed Cycleway Extension  

Description
This proposed cycleway and will be an extension of the existing facility south of Northcote Road, and in future it will extend to the Main North Road to the north. The project involves the installation of a signalised pedestrian/cycle facility on Northcote Road at the rail crossing. Northcote Road, the rail crossing alarms, and Vagues Road left turn out, will be included in the traffic signal phasing. The signals will operate in a similar manner to those installed where the existing railway cycleway crosses Fendalton Road, Glandovey Road, and Blighs Road.

The pathway will run from Northcote Road to Tuckers Road between the tracks and the waterway on the west side and is located in the Shirley/Papanui Community Board area.

The primary objectives of the project are as follows:
Construct a cycleway link along the railway corridor between Northcote Road and Tuckers Road.
Install traffic signals at the Northcote Road intersection with the cycleway.
Provide safe crossing points at all road intersections.
Ensure adequate lighting is provided.

The pathway will be 3 to 3.5m wide and will require a retaining wall at least on the track side of the path. Some landscaping is proposed at the Northcote Road end of the pathway where it links into the road and the existing culverts will be extended. The physical nature of the rail corridor, with the waterway nearby has left little scope for changes to the path alignment. Please click on the link below to view the consultation plans.

Construction is programmed to start in April 2009 at an estimated cost of $891,400.
 

Description of current stage:

 

Christchurch City Council, PO Box 237, Christchurch 8140, New Zealand